A critical hypervisor security patch has been released and needs to be rolled out as soon as possible. Which of the following steps can be taken to minimize
downtime for all guest VMs currently running?

A. In the next scheduled maintenance window, apply patch, reboot host, and wait for all VMs to come back online.

B. In the next scheduled maintenance window, migrate VMs to another host. Remove host from any availability clusters, patch host, reboot host, and place host
back into availability cluster.

C. In the next scheduled maintenance window, shut down all VMs, apply patch, reboot host, and wait for all VMs to come back online.

D. In the next scheduled maintenance window, migrate VMs to another host. Remove host from any availability clusters, unplug network cables from host, patch
host, reboot host, reconnect network cables, and place host back into availability cluster.

Explanation: