After the presentation, you are asked to explain the chart.
Assume you have applied a full risk-based testing strategy.

Which of the following answers would you expect to best describe the pie chart? 1

Which of the following answers would you expect to best describe the pie chart?

A. All the risk items have been covered with tests. No more risk items remain to test

B. According to the full risk-based testing strategy applied, it is very likely that the highest-risk items, tests
and bugs remain in the blue and red areas. Therefore, it is very risky to release the application

C. Only the lowest-risk items, tests and bugs should remain in the blue and red areas. Therefore the
application can be released at any time subject to management of the items identified in those areas

D. 97 percent of the risk items has been tested. No open bugs or test failures remain. Only 3 percent of
risk items remains to be covered by the remaining test

Explanation: