What is the difference between total float and free float?

You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wantsto know the difference between total float and free float. What is the difference between total float and free float? A. Total float is the amount of time […]

Read More

How many more communication channels will Ben’s project have next week?

Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many morecommunication channels will Ben’s project have next week? A. 140 B. 10 C. 325 D. 5 Explanation:Ben’s project will have 140 more communication channels because of the five additional stakeholders. […]

Read More

What is the to-complete performance index for this project?

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You havespent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget.What is […]

Read More

This is an example of what project execution technique?

You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 andrequires special hardware to electronically lock and open the doors. You’ve gathered the project team before they begin the installation for a hands-on training. As agroup you […]

Read More

What is Parkinson’s Law?

Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim isadding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not […]

Read More