You are the project manager for your organization. You are coaching Allen, a junior project manager, on how the details of the project’s critical path are calculated.
Examine the figure given below:

What is the critical path of this project?

A. ABEHJ

B. ACFGJ

C. ADGJ

D. ACFIJ

Explanation:
The critical path is discovered by summing the duration of each activity node in each chain of activities in the project network diagram. In this figure, the critical path
is ACFGJ, which is 26 days, the longest chain of activities in the project.
Incorrect Answers:
A: This path’s duration is 22 days.
C: This path’s duration is 15 days.
D: This path’s duration is 23 days.